Reference · Permitting

What your AHJ will want, and what only they can tell you

Describe the project and this lays out the approvals to open, the code articles in play, the order the inspections come in, and the documents review will ask for — then hands you the questions to put to your building department and your utility.

It does not know your jurisdiction, and will not pretend to. There are tens of thousands of authorities having jurisdiction in the United States. Which edition of the NEC, IBC, IRC or IFC each has adopted — and what it has amended on top — varies by state and by city and changes on adoption cycles. None of that is loaded here. Everything below is what usually applies, written so you can confirm it. The adopted edition is a question for your AHJ, and the questions are the point of the page.
Project type
Mounting
Storage
Grid export
Also true of this project
0 of 25 ticked

Approvals to open

Separate tracks, often separate departments. The utility ones are not the AHJ's and do not move on its schedule.

Codes in play

The families and articles that govern this scope. Which EDITION of each applies is the AHJ's to state — see the questions below.

Inspection sequence

The usual order. Anything that gets covered up has an inspection before it does.

Document pack

What review will ask for, and who has to produce it.

Ask the building department

This is the part no checklist can answer for you. The first question is the one that decides your whole plan set.

  1. Which edition of the NEC have you adopted, and do you have local amendments to it?
  2. Which building code edition applies, and which edition of ASCE 7 does it reference for wind and snow?
  3. Do you require a separate electrical permit, or is it part of the building permit?
  4. Do you accept electronic plan submission, and do you use SolarAPP+ or another automated review?
  5. What is your current plan review turnaround, and your inspection lead time?
  6. Which inspections do you require, and in what order? Is a mounting or pre-cover inspection needed before the modules go on?
  7. Do you require a licensed engineer's stamp on the structural letter, and must that engineer be licensed in this state?
  8. What roof access pathways and setbacks do you enforce, and does that differ for this occupancy?
  9. Is there anything about solar submissions that you see done wrong most often?

Ask the utility

A different organisation, a different queue, and usually the longer one.

  1. Which interconnection process applies at this system size, and what is the queue time today?
  2. Which inverter grid-support certification do you require, and which IEEE 1547 profile or settings?
  3. Do you require export limiting, and how must it be demonstrated?
  4. Is a witness test required, and who schedules it?
  5. What has to be complete before permission to operate is issued?
Worksheet as plain text

Where the adopted edition actually comes from

Model codes are written nationally and adopted locally. The NEC is published by the NFPA, the IBC, IRC and IFC by the ICC — but none of them applies anywhere until a state or a local government adopts it, usually some editions behind current, and usually with amendments. Two towns an hour apart can be on different editions.

  1. The model code is publishedNFPA and ICC issue on a three-year cycle.
  2. A state adopts an editionOften with statewide amendments, sometimes leaving it to localities.
  3. The local AHJ adopts and amendsIt may lag the state, and may add its own requirements.
  4. Your plan set is reviewed against thatWhich is why the edition is the first thing to establish.

The authoritative answer is the building department itself. The NFPA and ICC both publish adoption maps that are a reasonable starting point, and a growing number of jurisdictions run automated residential review through SolarAPP+ — but confirm any of it with the AHJ before drawing.

The three things that go wrong

Starting interconnection late

The utility is not the AHJ. It has its own application, its own queue and its own timescale, and permission to operate comes after both tracks finish. On most projects the utility, not the building department, is the critical path.

Missing an inspection that cannot be redone

Anything that gets covered — pile embedment, roof attachments and flashings, buried conduit — has an inspection before it is covered. Finding out afterwards means opening it back up.

Designing against the wrong edition

Rapid shutdown, labelling and busbar rules all moved between recent NEC editions. A plan set drawn to the wrong one is a redraw, not a correction.

Questions, for a residential rooftop system

The worksheet above tailors these to your project. Rendered here so they are readable without it.

  1. Which edition of the NEC have you adopted, and do you have local amendments to it?
  2. Which building code edition applies, and which edition of ASCE 7 does it reference for wind and snow?
  3. Do you require a separate electrical permit, or is it part of the building permit?
  4. Do you accept electronic plan submission, and do you use SolarAPP+ or another automated review?
  5. What is your current plan review turnaround, and your inspection lead time?
  6. Which inspections do you require, and in what order? Is a mounting or pre-cover inspection needed before the modules go on?
  7. Do you require a licensed engineer's stamp on the structural letter, and must that engineer be licensed in this state?
  8. What roof access pathways and setbacks do you enforce, and does that differ for this occupancy?
  9. Is there anything about solar submissions that you see done wrong most often?